First Production Cutover

Use this checklist for first real tenant traffic.

Preconditions

  • Durable database configured (STORE=pg)
  • Ops token management and key rotation process defined
  • Webhook endpoints reachable with signature verification enabled
  • Rollback owner and incident comms owner assigned

Required gates before cutover

npm run test:ops:onboarding-policy-slo-gate
npm run test:ops:onboarding-host-success-gate
npm run test:ops:production-cutover-gate
npm run test:ops:go-live-gate

Cutover sequence

  1. Deploy API + worker paths.
  2. Run onboarding runtime loop for at least one real host.
  3. Execute first paid call and verify receipt.
  4. Confirm conformance matrix reports ready=true for selected hosts.
  5. Enable pilot tenant/flow with bounded limits.
  6. Monitor escalation, reversal, and delivery queues during first live window.

Go / No-Go

Go only if all are true:

  • All gates green
  • Receipt verification and closepack export pass
  • No unbounded dead-letter growth
  • Escalation resolution path is functional end-to-end

Rollback triggers

Rollback immediately if any of the following appear:

  • Verify path fails closed unexpectedly for healthy traffic
  • Escalation queue cannot be drained
  • Reversal/unwind processing stalls
  • Receipt verification parity breaks