Trust OS v1 Execution Plan (6 Weeks)¶
This plan maps strategy into a launch-ready execution sequence.
End-State Targets¶
- TTFVR p50 <= 8 minutes
- onboarding completion >= 70% external cohort
- first paid-call+verification success >= 99.0%
- all P0 launch gates green for two consecutive weeks
Weekly Sequence¶
- Week 1: onboarding state machine + failure taxonomy lock
- Week 2: auth/session/bootstrap reliability hardening
- Week 3: managed wallet funding + first paid run golden path
- Week 4: settlement/reversal idempotency + dispute hardening
- Week 5: SRE/security/compliance launch gate prep
- Week 6: controlled launch with command center
Non-Negotiables¶
- no policy bypasses for paid actions,
- no launch with unresolved P0 security findings,
- deterministic receipts required for first-run success.
Full Plan¶
planning/sprints/state-of-the-art-v1-6-week-plan.mdplanning/jira/state-of-the-art-v1-backlog.json